# CP-07 (03) Priority of Service — NIST 800-53 Rev5 control

> FedRAMP Consolidated Rules for 2026 v2026.07.14.01 · updated 2026-07-14
> Canonical page: /control/cp-7.3

Canonical id: `cp-7.3` · family `CP`

> Develop alternate processing site agreements that contain priority-of-service provisions in accordance with availability requirements (including recovery time objectives).

_Control title and statement: NIST SP 800-53 Rev5 catalog (the pinned commit is in `/api` under `control_text`). The FedRAMP rules reference these controls by id only; everything below is what FedRAMP says about this id._

## Rev5 baseline membership

- certification class C
- certification class D

## Key Security Indicators that reach it

- `KSI-RPL-ARP` — Aligning Recovery Plan (Recovery Planning)
  The alignment of recovery plans with defined recovery objectives is persistently reviewed.

## FedRAMP guidance

_No FedRAMP-specific guidance attaches to this control._